Chester Gate Remediation 1st Phase Works Completed

December 18th, 2019

Following our site start in November the 1st stage of the remediation works has been completed ready for the Christmas shut down. Really good progress has been made on site with all the contamination been took care of to allow the site to progress to the next stage. All Topsoil has been removed and the made ground removed ready to commence clay capping works and removal of all existing roads and sewers. We will commence the new section of Roads & Sewers straight after the Christmas break. We have also completed the Existing sewer diversion works during the first 4 weeks on site.